Showing posts with label Project Reporting. Show all posts
Showing posts with label Project Reporting. Show all posts

Oct 18, 2012

Status Your Project with the WBS

The WBS serves as a perfect framework for project status reporting

Your WBS is the list of everything that needs to get done to complete the project.  It’s a ready-made framework for monitoring and statusing the project.

Let’s begin with the basic structure of the WBS:

WBS Code WBS Description
100 Project Management
200 Product
200.1     Product Requirements
200.1.1         Stakeholder Requirements
200.1.2         System Requirements
200.2     Product Design
200.3     Product Build
200.4     Product Testing
200.5     Product Deployment

If we are going to use this for reporting, we need to include who’s in charge of delivering each WBS Item.  Generally, this can be the Project Manager for that piece of work.

WBS Code WBS Description Responsible
100 Project Management PM
200 Product n/a
200.1     Product Requirements n/a
200.1.1         Stakeholder Requirements Bill F
200.1.2         System Requirements Jane T
200.2     Product Design John X
200.3     Product Build Mary G
200.4     Product Testing Keith D
200.5     Product Deployment Sara S

The updated table above shows which manager or lead has responsibility for delivering the work described in each WBS entry.  The items 200 – Product, and 200.1 Product Requirements have no designated responsible person because all the work under them are parcelled out to the work subitems under them.

Now we need to update the table to show the status.

WBS Code WBS Description Responsible Status
100 Project Management PM n/a
200 Product n/a Started
200.1     Product Requirements n/a Started
200.1.1         Stakeholder Requirements Bill F Completed
200.1.2         System Requirements Jane T 70%
200.2     Product Design John X NYS
200.3     Product Build Mary G NYS
200.4     Product Testing Keith D 10%
200.5     Product Deployment Sara S NYS

In the above update, we see that item 200.1.1 has been completed, 200.1.2 is 70% completed, some of the work are Not Yet Started.  Work 100 – Project Management will have no status because it is ongoing work, while 200 and 200.1 will have only Started at their level. They will become Completed when all the sub-items under them have been completed.

The problem with the above is that it says nothing about whether the project is going according to schedule, going ahead, or being delayed.

For that we can use Earned Values to show the status of the work.

And because the status date of each individual work item may differ, it might be useful to add another column to indicate the as-of status date for that piece of work.